I am looking for installation instructions for chemical anchors in upward direction and load test instruction and device.

Posted by Mehdi Saberi16 days ago
I am looking for installation instructions for chemical anchors in upward direction and load test instruction and device.

I used HILITI PROFIS software to design anchors
for a powerhouse. the anchors will be installed upward in to concrete ceiling.
the software proposed HIT-HY 200 V3+ HIT Z. each 4 anchors will connected to a
base plate and support 10 kN of loads. I reached you out to get your advice
about installation procedure in upward direction and pull out test procedure
and devices. Thanks and looking forward to herring from you Mehdi Saberi Klohn
Crippen Berger

pull testing,concrete ceiling,direction

1 Reply
Posted by Ashley Couron13 days ago
Hilti Verified

Hi Mehdi,

Please refer this response from a previous question.

Regards,
Ashley